Construction project environmental protection facilities completion and commissioning time publicity
According to the Regulations on the Administration of Environmental Protection for Construction Projects and the Announcement on the Interim Measures for the Acceptance of Environmental Protection for the Completion of Construction Projects (Environmental Assessment (2017) No. 4), etc., construction projects should disclose the following information to the public on their websites or in other ways that are convenient for the public to know:
(1) After the completion of the environmental protection facilities supporting the construction project, the completion date shall be disclosed;
(2) Before commissioning the environmental protection facilities supporting the construction project, the start and end date of debugging shall be disclosed.
ShanDong Orient HongYe Chemical Co., Ltd. 70,000 tons of polypropylene technical upgrade project, 20,000 tons/year oil tree project is located in HouZhen, ShouGuang Sea Chemical Park JinYuan Road No. 15. Project annual output of polypropylene 180,000 tons/year, 20,000 tons/year petroleum resin.
The project shall make the following announcements as required:
(1) Completion date
June 15, 2022
(2) Debugging time
February 3, 2023 - March 3, 2023
(3) The way the public requests information
The public can consult the construction unit by telephone or letter after the relevant information is made public.
(4) Contact information of the construction unit
Contact: Wang ZongJun
Contact number:15965088070